DIAB-220 Initial Risk Register

Training-use boundary: This is a fictional teaching artifact for clinical project-management practice. It is not a protocol, SAP, consent form, regulatory submission, SOP, validation package, or sponsor-approved record. Real study use requires medical, statistical, regulatory, quality, legal, privacy, safety, and operational review.
RiskCause / SignalInitial RatingAccountable OwnerTriggerMitigation Before InitiationContingency / EscalationReview Cadence
Endpoint credibilityEndpoint data are incomplete, inconsistent, mistimed, or not traceable.HighMedical / Biostatistics / DataEndpoint-critical procedure or transfer lacks tested evidenceMap endpoint-critical procedures, vendors, systems, visit windows, and data checks before initiation.Escalate to governance if the primary endpoint path cannot be proven before SIV release.Monthly until startup release; weekly if trigger appears
Enrollment feasibilityTarget population or criteria produce slower enrollment or high screen failure.HighClinical Operations / Site FeasibilityScreening assumptions depend on unverified site enthusiasmRequire site feasibility evidence, screening assumptions, country/site mix, and rescue triggers.Escalate if forecasted FPI or enrollment rate lacks site-level evidence.Monthly until startup release; weekly if trigger appears
Participant protectionConsent, safety follow-up, privacy, burden, or communication risk is underestimated.HighMedical / Safety / Regulatory / Patient EngagementParticipant-facing material, safety pathway, or burden review remains incompleteReview with Medical, Safety, Regulatory, Ethics, Patient Engagement, and Quality.Escalate immediately if consent, safety reporting, or privacy controls are not ready.Monthly until startup release; weekly if trigger appears
Vendor/system readinessVendor, CRO, EDC, IRT, eCOA, lab, imaging, or device workflow is not ready when sites activate.MediumPriya Raman / Victor Stein / Owen FletcherUAT, transfer test, help desk, or system release evidence is missingCreate vendor readiness checklist, UAT evidence, interface map, and escalation path.Hold release of endpoint-critical work until acceptance evidence is complete.Monthly until startup release; weekly if trigger appears
Budget/scope driftOriginal budget does not reflect actual protocol, vendor, site, or data requirements.MediumMaya Desai / Procurement / FinanceProtocol or vendor assumption changes without budget updateTie budget assumptions to WBS, SOW, pass-throughs, timeline, and contingency.Route change order or rebaseline decision through governance.Monthly until startup release; weekly if trigger appears
Inspection evidence gapThe team cannot prove what was decided, why, by whom, and with what evidence.HighGrace Kim / Helen Park / PMDecision, approval, training, or oversight record is missing from the evidence mapSet TMF plan, decision log, issue log, risk register, and evidence package before initiation.Escalate when an essential record cannot be retrieved or reconstructed.Monthly until startup release; weekly if trigger appears

PMBOK Use

This file is the project-specific seed for the RAID log and risk register. Lauren should transfer each accepted risk into the live project risk register, preserve the owner and trigger fields, and ask Daniel Liang to review any risk that crosses participant protection, primary endpoint, inspection-readiness, or governance-decision thresholds.